Cost to build 2 bedroom house

Have you ever considered building an apartment otherwise called a House? Or have you ever wondered the monetary costs involved in building a House? Or do you know the estimated cost in case you want to start building a house? This Article seeks to assist you by giving a rough estimate of the cost of building a house and how you may go about building such a house.

Cost to build 2 bedroom house

Cost of Building a 2 Bedroom Bungalow in Nigeria 2023

Before you dig earth, make sure you have all required APPROVED documents for the construction process, viz a viz:

  • Architectural drawings.
  • Structural drawings.
  • Mechanical drawings.
  • Electrical drawings.

Some people destroy the earth without some of these drawings and hope for the best. That is an incorrect mindset. Please follow the steps in the correct order.

A case sample of the design indicated below was used for this analysis. We’ve merely posted rough renderings of the design to serve as a starting point for this price.

In calculating the cost of building a 2 bedroom bungalow in Nigeria, it is advisable to break down the construction process into stages. This is the norm and is actually helpful in planning your progress. For a bungalow, we can split the construction stages into:

  • Earthwork and excavation
  • Foundation (German floor).
  • DPC to lintel level Stage.
  • Roofing Stage.
  • Plastering / Finishing Stage.
  • Painting Stage

Cost of Foundation (German Floor)

This is the first stage of construction and it includes setting out, digging, concrete work, block laying, backfilling, and flooring as the processes in this stage.

Material Requirements For Earthwork And Excavation
  • Site clearance Labour only (150 sqm) @ NGN 100 per m2 = NGN 15,000
  • Topsoil removal labour only (150 sqm) @ NGN 500 per m2 = NGN 75,000
  • Setting out (excavation / building line) materials = NGN 48,556.08
  • Setting out (excavation / building line) labour only = NGN 90,175.98
  • Trench excavation (78 m) @ NGN 600 per meter = NGN 46,800
  • Back filling and removal of surplus (labour only) = NGN 11,900
  • Laterite Filling (10tyres truck) – 2 trips @ NGN 15,000 per trip = NGN 30,000
  • Hardcore (10tryes truck) – 2 trips @ 50,000 per trip = NGN 100,000
  • Laying Hardcore and Ramming of laterite (labour only) = NGN 40,000

Estimated cost of earthwork and excavation = NGN 457,431.67

Material Requirements For Earthwork Support
  • 87 Length of 1″ x 12” x 3.60m long plank @ NGN 1,200 each = NGN 104,400
  • 49 Length of 4″ x 4” x 3.60m for strutting @ NGN 800 each = NGN 39,200
  • 20 Length of 2″ x 2” x 3.60m for bracing @ NGN 600 each = NGN 12,000
  • 1 bags Nail of various Sizes (3″, 4″ & 5″ Sizes) @ NGN 9,000 per bag = NGN 9,000
  • Labour for fixing Earthwork support (89 sqm) @ NGN 500 per sqm = NGN 44,500
  • 11 nos (4 litre gallon) Antitermite treatment @ NGN 3,600 per gallon = NGN 39,600
  • Labour = NGN 20,000
  • 2 rolls Damp proof membrane @ NGN 5,000 per roll = NGN 10,000

The estimated cost of earthwork support = NGN 278,700.

Material Requirements for Blinding
  • 2 bags of cement @ NGN 3,800 each = NGN 7,600
  • 13 tonnes stone dust @ 2,500 per tonne = NGN 32,500
  • Labour @ NGN 700 per bag = NGN 1,400

The estimated cost of concrete work = NGN 41,500.

Material Requirements For Foundation Footing

This is done in the trench with the ratio (1:2:4)

  • 62 bags of cement @ NGN 3,800 each = NGN 235,600
  • 16 tonnes stone dust @ 2,500 per tonne = NGN 40,000
  • 15 tonnes granite @ 2,750 per tonne = NGN 41,250
  • Labour @ NGN 700 per cement bag = NGN 43,400

The estimated cost of foundation footing = NGN 360,250.

Material Requirements For Blockwork in Foundation

Mortar mix is in the ratio (1:6)

  • 2 tonne sand @ NGN 2,500 per tonne = NGN 5,000
  • 6 bags of cement @ NGN 3,800 each = NGN 22,800

Concrete for filling (1:4:8)

  • 4 tonne sand @ NGN 2,500 per tonne = NGN 10,000
  • 8 bags of cement @ NGN 3,800 each = NGN 30,400
  • 3 tonnes granite @ 2,750 per tonne = NGN 8,250
  • 360 pieces of 9-inch vibrated blocks (including 10 percent wastage) @ NGN 270 each = NGN 97,200
  • Labour for blockwork @ NGN 60 per block = NGN 21,600
  • Labour for filling concrete @ NGN 2,000

The estimated cost of laying foundation blocks = NGN 197,250.

Material Requirements for Ground Floor Slab

Ground Floor Slab with the ratio (1:2:4)

  • 117 bags of cement @ NGN 3,800 per bag = NGN 444,600
  • 30 tonne stone dust @ NGN 2,500 per tonne = NGN 75,000
  • 29 tonnes granite @ 2,750 per tonne = NGN 79,750
  • Labour for casting concrete @ NGN 700 per bag = NGN 81,900
  • 36 Length of 1″ x 12” x 3.60m long plank @ NGN 1,200 each = NGN 43,200
  • 1 bag Nail of various Sizes (3″, 4″ & 5″ Sizes) @ NGN 9,000 per bag = NGN 9,000
  • Labour for capenter on formwork @ NGN 19,500
  • 6 roll BRC Mesh Ref 142 (15m x 2.1m) @ NGN 18,000 per roll = NGN 108,000

The estimated cost of flooring = NGN 860,950

Cost of Construction From Damp Proof Course (D.P.C) To Lintel Level

This is the next stage in the construction process and begins where the German floor ends. It covers the main block work including wall partitions for the various spaces in the house. The materials listed below are just estimates of what you get in the 4-bedroom flat sample above. Again, ensure you get a Bill of Quantities for your building plan as that’s the only way to know the exact material requirements for your house. This stage ends at the roof level.

Material Requirements for Block work Above DPC
  • 1,110 nos 225mm Blocks @ NGN 270 per block = NGN 299,700
  • 980 nos 150mm Blocks @ NGN 230 per block = NGN 225,400

Mortar (1:6) mix for jointing

  • 34 bags of Cement @ NGN 3,800 per bag = NGN 129,200
  • 9 ton Stone dust @ NGN 2,500 per ton = NGN 22,500
  • Labour for Blockwork @ NGN 45 per block = NGN 94,050

Estimated cost of block work = NGN 770,850.

Material Requirement for Lintel Casting

Lintel is casted in the ratio (1: 2: 4)

  • 12 bags Cement @ NGN 3,800 per bag = NGN 45,600
  • 3 ton stone dust @ NGN 2,500 per ton = NGN 7,500
  • 3 ton Granite @ NGN 2,750 per ton = NGN 8,250
  • Labor for casting Concrete @ NGN 700 per bag = NGN 8,400

Formwork (to sides and soffit )

  • 22 length 1″ X 12″ X 3.6m (Plank) @ NGN 1,200 per length = NGN 26,400
  • 22 length 2” x 3″ x 3.6m plank @ NGN 450 per length = NGN 9,900
  • 25 length 2” x 2″ x 3.6m plank @ NGN 350 per length = NGN 8,750  
  • 0.24 bag of Nail various Sizes (3″, 4″ & 5″ Sizes) @ NGN 9,000 per bag = NGN 2,160
  • Carpenter on formwork (24 sqm) @ NGN 500 per sqm = NGN 12,000

Reinforcement

  • 13 length 10mm diameter @ NGN 1,650 per length = NGN 21,450
  • 14 length 12mm   diameter @ NGN 3,400 per length = NGN 47,600
  • 0.13 roll Binding Wire (25kg / roll) @ NGN 11,500 per roll = NGN 1,495
  • Iron benders on reinforcement (246 kg) @ NGN 50 per kg = NGN 12,300

The Estimated cost for Lintel is NGN 212,305

Cost of Roofing A 2 Bedroom Bungalow Stage

Material Requirements for Roof Covering And Carcassing

The following hardwood is treated before use.

  • 29 length of 100 x 150mm hardwood timber (wall plate) @ NGN 320 per length = NGN 9,280
  • 66 length of 50 x 150mm hardwood timber (tie beam) @ NGN 400 per length = NGN 26,400
  • 61 length of 50 x 150mm hardwood timber (Rafter) @ NGN 400 per length = NGN 24,400
  • 71 length of 50 x 100mm hardwood timber (kingpost/struts) @ NGN 400 per length = NGN 28,400
  • 223 length of 50 x 75mm hardwood timber (purlins) @ NGN 300 per length = NGN 66,900
  • Labour on carcassing (1618  m) @ NGN 45 per m = NGN 72,495
  • Roof covering + capping (285 m2) @ NGN 5,000 per m2 = NGN 1,425,000
  • 63 nos Hip plate and trimmer @ NGN 900 per plate = NGN 56,500
  • 720 nos Roof nails (Galvanised nails) @ NGN 35 per nail = NGN 25,200
  • Labour for roof covering (285 m2) @ NGN 500 per m2 = NGN 142,500  

Total Estimated Cost for the roofing stage = NGN 1,877,075.

Cost of Finishing Stage

This stage includes plastering, wiring, plumbing, fixing of windows, doors, tiles, and other essentials. The cost here varies regarding the quality of materials you use. Below is an estimate for a very modest finishing of the design above.

Material Requirements For Floor Finishing

Tiling (Floor)

  • 450 x450 x10mm thick Vitrified floor tiles (78 m2) @ NGN 2,100 per m2 = NGN 163,800
  • 889 NOS Ditto skirting tiles @ NGN 50 each = NGN 44,450
  • 14 bags of Cement for fixing tiles @ NGN 4,600 per bag = NGN 64,400
  • Labour for Tiling (98 m2) @ NGN 400 per m2 = NGN 39,200

Screeding (floor)

25 mm screeded bed C & S (1:4)

  • 21 bag of Cement @ NGN 3,800 per bag = NGN 79,800
  • 4 ton Stone dust @ NGN 2,500 per ton = NGN 10,000
  • Labour for screeding (98 m2) @ NGN 400 per m2 = NGN 39,200
Material Requirements For Wall Finishing

Plastering (wall)

13mm screeded bed C & S (1:4)

  • 32 bags of cement @ NGN 3,800 per bag = NGN 121,600
  • 3 ton stone dust @ NGN 2,500 per ton = NGN 7,500
  • Labour for plastering (307 m2) @ NGN 450 per m2 = NGN 138,150

Tiling (wall)

  • 200 x 400 vitrified tiles (116 m2) @ NGN 3,500 per m2 = NGN 406,000
  • 16 bags of Cement for  fixing tiles @ NGN 4,600 per bag = NGN 73,600
  • Labour for Tiling (116 m2) @ NGN 400 per m2 = NGN 46,400

Screeded backing (wall)

20 mm screeded bed C & S (1:6)

  • 14 bags of Cement @ NGN 3,800 per bag = NGN 52,440
  • 3 ton of Sand @ NGN 2,500 per ton = NGN 7,500
  • Labour for screeding (116 m2) @ NGN 400 per m2 = NGN 46,400
Material Requirements For POP Ceiling
  • 56 bags of P.O.P Cement @ NGN 4,000 per bag = NGN 224,000
  • 6 packs of Concrete nails @ NGN 2,500 per pack = NGN 15,000
  • 42kg sponge @ NGN 1,650 per kg = NGN 69,300
  • 2 roll of Binding wire @ NGN 10,000 per roll – NGN 20,000
  • 2 roll imperial soap @ NGN 1,500 per roll = NGN 3,000
  • 5 litres groundnut oil @ NGN 3,000 per litre = NGN 15,000
  • 6 length 50 x 50mm hardwood noggins @ NGN 250 per length = NGN 1,500
  • Labour on ceiling (100 m2) @ NGN 1,700 @ NGN     170,000

Total Estimated Cost for the Finishing Stage is NGN 1,858,240

Cost Of Painting Stage

Material Requirements For Painting Work

Wall Screeding (To Receive Paint)

  • 2 bags of Screeding cement (white cement) @ NGN 4,600 per bag = NGN 9,200
  • Labour for screeding (307 m2) @ NGN 200 per m2 = NGN 61,400

Floating

  • 2 bags of P.O.P Cement @ NGN 4,600 per bag = NGN 9,200
  • Labour for floating (307 m2) @ NGN 200 per m2 = NGN 61,400

Painting and Decoration

  • 5 drum of Dulux Emulsion/texcote paint (20Litres Drum) @ NGN 20,000 per drum = NGN 100,000
  • Labour for Painting (307 m2) @ NGN 180 per m2 = NGN 55,260

Total Estimated Cost for the Painting Stage = NGN 296,460

Cost Of Doors, Windows, Burgalary

Material Requirements For Doors And Windows

Steel Doors

  • 2 nos 900 x 2100mm high @ NGN 50,000 each = NGN 100,000

Wooden Doors

  • 3 nos Overall size 900 x 2100mm high @ NGN 37,800 each = NGN 113,400
  • 3 nos Overall size 750 x 2100mm high @ NGN 31,500 each = NGN 94,500

Windows

  • 3 nos Window size 600mm x 900mm high @ NGN 10,800 each = NGN 32,400
  • 4 nos Window size 1500mm x 1500mm high @ NGN 32,400 each = NGN 129,600
  • 4 nos Window  size 1800mm x 1500mm high @ NGN 54,000 each = NGN 216,000

Steel burglary bars

  • 3 nos Window size 600mm x 900mm high @ NGN 3,780 each = NGN 11,340
  • 4 nos Window size 1500mm x 1500mm high @ NGN 15,750 each = NGN 63,000
  • 4 nos Window  size 1800mm x 1500mm high @ NGN 18,900 each = NGN 75,600
  • Other ancillaries sum budget @ NGN 34,200
  • Labour sum budget @ NGN 30,000

Total Estimated Cost for Doors and Windows = NGN 900,040

Cost Of Mechanical And Pipeline Services

Material Requirements for Mechanical Works

Mechanical Installations

  • 3 nos Water Closet; Approve WC, 7.5 cistern, complete with fittings for installation @ NGN 27,500 each = NGN 82,500
  • 3 nos Approved (WHB) wash hand basin, complete with installation accessories @ NGN 15,000 each = NGN 45,000
  • 1 nos Approved (WHB) wash hand basin, double bowl, double drainer , complete with installation accessories @ NGN 35,000 each = NGN 35,000
  • 1 nos Approved double drainer, double bowl, stainless steel sink with mixer tap, with installation accessories complete @ NGN 25,000 each =  NGN 25,000
  • 3 nos Shower tray + shower head @ NGN 20,000 each = NGN 60,000
  • 2 nos Ariston water heater containing 20 litres capacity @ NGN 50,000 each = NGN 100,000
  • 3 nos 50mm diameter stainless trapped floor drains @ NGN 2,500 each = NGN 7,500
  • 2 nos Stainless steel soap dish fixed to wall @ NGN 3,500 each = NGN 7,000
  • 2 nos Stainless towel rail fixed to wall  NGN 3,500 each = NGN 7,000
  • 3 nos Stainless toilet roll holder fixed to wall @ NGN 2,500 each = NGN 7,500
  • 2 nos Mirror; 4mm silvered float glass; 460 x 610mm with arrissed edges and mounted on wall @ NGN 15,000 each = NGN 30,000
Material Requirements for Pipeline Works

Inspection Chamber

  • 2 nos Construction of Inspection chamber size 450 x 450 x 450mm deep complete with earthwork and other associated work @ NGN 15,000 each = NGN 30,000

Man Hole

  • 1 nos Construction of Manhole size 600 x 600 x 600mm deep complete with earthwork and other associated work @ NGN 17,000 each = NGN 17,000

Soak Away Pit

  • Construction of Soak away pit of approved size @ NGN 200,000    

Septic Tank

  • Construction of Septic tank of approved size, complete with associated works @ NGN 200,000
  • Provisional sum for all piping and builders work (sum budgeted) @ NGN 150,000

Estimated Cost of Mechanical and Plumbing Services = NGN 1,003,500

Cost Of Electrical Services

Installations

Allow a provisional sum for electrical installations in connection with Electrical Installations @ NGN 300,000

How much does it cost to build a 2 bedroom tiny house?

The average cost of building a tiny house is $20,000 to $50,000. This includes the land, materials, and labor costs. Tiny houses are often built on trailers so they can be moved easily. The average cost of building a tiny house on wheels is $20,000 to $40,000 depending on the size and features of your dream home.

How much does it cost to build a 3 bedroom 2 bath house?

The average cost of building a 3 bedroom 2 bath home is between $200 and $400 per square foot. This means that the total cost of building this type of home would be between $60,000 and $120,000 if you hired a contractor to do the work for you.

The total cost for building this type of house would vary depending on how many square feet you wanted your home to have as well as what types of materials you were going use for construction (wood or vinyl siding). On average though, it costs about $200 per square foot for framing, plumbing and electrical work; about $100 per square foot for drywall installation; about $50

The average cost to build a 2 bedroom house is $250,000. The average cost to build a 2 bedroom tiny house is $50,000.

The estimated cost of building a 3 bedroom 2 bath house is $350 per square foot. The average size of a 3 bedroom 2 bath house is about 1,500 square feet.

The estimated cost for building this type of home would be $525,000.00.

The average cost for building a 3 bedroom 2 bath house ranges from $300 – $500 per square foot depending on the location of the property and the contractor used for construction.

The average cost to build a 2 bedroom house is $250 per square foot. This includes the labor, materials and permits. The average size of a 2 bedroom house is about 1,200 square feet. So, if you want to build a 2 bedroom house that costs $250 per square foot, it will cost about $300,000 to build it.

The cost of building a 2 bedroom home can vary depending on where you live and the size and style of the home. For example, in some parts of the country where land is expensive and labor costs are high, it could cost as much as $500 per square foot to build a 2 bedroom home.

The two factors that affect how much it costs to build a new home are:

The size of the home (or how many square feet)

How expensive it is to buy land (or what your lot costs)

The cost to build a 2 bedroom house varies widely depending on the location and size of the home. The average cost of a 2 bedroom house in the United States is $200,000. This is an average and does not include other costs such as land preparation or permits. The cost to build a 2 bedroom house can be as low as $30,000 or as high as $500,000 depending on where you live and what type of materials you use.

The average cost to build a 2 bedroom house in California is $300 per square foot, which means that a 2000 square foot home would cost about $600,000 to build. This does not include any furnishings or appliances for the home, but it does include labor costs and materials used in construction of the home itself.

The average cost to build an 1800 square foot home in Ohio is about $150 per square foot. This includes labor costs but no taxes or permits required by local government regulations.

The cost to build a 2-bedroom house can vary greatly depending on the size and location of the house. The average cost for a 2-bedroom, 1-bathroom home in the United States is $75,000, according to CostHelper. However, this is just an average and does not take into account regional differences in construction costs.

If you’re looking to build a 2-bedroom house from scratch, start by selecting the right land for your new home. If you already have land that fits your needs, skip ahead to Step 2. Otherwise, keep reading for more info on finding land and getting started on your project.

Step 1: Find Land for Sale

The first step in building your own home is finding a suitable plot of land to build on. There are several different options available depending on what type of property you’re looking for and where you live:

Buy an existing home and renovate it: If prices are too high in your desired neighborhood or city, consider buying an existing home instead of paying more money to build one from scratch.

How much does it cost to build a 2 bedroom tiny house?

The average cost to build a tiny house is between $10,000 and $40,000. That includes everything from the land to the house itself. But if you’re looking for something more permanent, then you’ll need to consider how much it will cost to build a 3 bedroom 2 bath house.

The average home price in America is around $200,000. It costs about $30 per square foot to build a home that size. So if you want a 3 bedroom home with 2 baths, that means it will cost you about $180 per square foot to build your dream home. This can vary depending on where you live and what type of materials you choose though.

How much would it cost to build a 3 bedroom 2 bath house?

Building a 3 bedroom 2 bath home can cost anywhere from $200 per square foot up to $300 per square foot or more depending on where you live and what type of material you want for your walls, roof and floors etc… The average cost for materials for this type of home would be about $90 per square foot for materials alone (not including labor).

A 2 bedroom tiny house design can range in cost from $10,000 to $20,000. With the average price being around $15,000. The cost of building a tiny house varies greatly depending on the builder and their experience, as well as the location where you live. The average cost to build a tiny house is between $10 and $30 per square foot. This means that if your home is 1,000 square feet then expect to pay anywhere between $10,000 and $30,000 for construction costs alone.

The average price of building a 3 bedroom 2 bath house ranges from $150 per square foot up to $250 per square foot depending on the size of your home and what features are included. If we assume that our hypothetical family needs at least 1,500 square feet of living space then they should expect to pay somewhere between $225,000 and $475,000 for construction costs alone! That’s not including fixtures or landscaping which could easily add another 30% on top of those numbers!

The answer depends on many factors. The first thing you need to do is decide what type of house you want to build and how much money you want to spend.

The average cost of building a two-bedroom tiny house is $20,000-$50,000 depending on the size of your land, the size of your home and whether or not you have any building experience. If you are looking for something more affordable but still want a small space with all the amenities, check out our article on building small homes for less than $20k.

How much does it cost to build a 2 bedroom 2 bath house?

The average cost for a two-bathroom house is around $200 per square foot, which means that an average sized 2-bathroom home could cost as much as $400,000 just for materials alone! This does not include labor costs (which can add thousands more to your final bill). So if you’re looking for a 2-bedroom home with 2 full baths don’t expect it to be cheap!

The cost to build a 2 bedroom house will depend on the size and amenities of your new home. The average cost for a 2 bedroom house is $75 per square foot, according to data from the U.S. Census Bureau.

To get a more accurate estimate of the cost of building your own 2 bedroom home, use our free calculator below:

Average Cost to Build a 2 Bedroom House

The average cost to build a two-bedroom house is $75 per square foot. That’s based on national averages, so if you live in an area that is more expensive than average, expect to pay more than that amount. On the other hand, if you live in an area where costs are lower than average, you might be able to afford more for your home for less money overall by paying less per square foot for construction materials and labor costs.

But before we get into how much it will cost to build or buy a 2 bedroom house, let’s look at what goes into building a home from start to finish.

The cost of building a house depends on the size and location of the home, and on the contractor you choose.

The average cost of building a 2,200-square-foot, single-story home in the U.S. is $220 per square foot, according to a report by home construction company KB Home. This includes all costs related to materials and labor. The average cost of building a 2,200-square-foot, two-story home is $270 per square foot.

For example, if you wanted to build a 2,200-square-foot house in Omaha, Nebraska (at $220 per square foot), it would cost about $460,000 before taxes or permits are included. In contrast, if you wanted to build a 3,600-square-foot house in San Francisco (at $270 per square foot), it would cost about $1 million before taxes or permits are included.